Case Study: Southeast Asia

Scalable Power to Match Industrial Park Growth in Southeast Asia

Project Summary

Powerphase recently installed two Turbophase modules at a Malaysian high-tech park, one of several projects it has underway in Asia. Ensuring reliable and efficient natural gas capacity is a challenge in the fast-growing Southeast Asian grid. Southeast Asia’s hot climate is a challenge for efficient CCGT operation because hotter ambient temperatures reduce air density and GT combustion efficiency. Turbophase can boost performance in hot conditions, and has a small footprint that minimizes infrastructure needs where there is limited space. Developing island infrastructure can be challenging due to limited land availability. Turbophase technology is modular, compact, and can be integrated into an existing plant’s footprint so Southeast Asian plant operators don’t have to undertake new land, transmission, or fuel supply pipeline surveying, permitting, design, and construction.

Powerphase takes a consistent engineering approach for all its projects. The Turbophase system implementation plan began with a feasibility study, followed by a turnkey pilot project and full implementation designed to support future growth. Powerphase engineers estimate that the power plant could increase its generating output by 10 percent, with 8 Turbophase modules, while building out far less than tenth of the plant’s current footprint.

Powerphase permitted the project in May 2017, installed the Turbophase system within two months, and began pilot operation in late October. Powerphase will complete the pilot run in 60 days. Powerphase anticipates the project will be fully operational by Summer 2018 with the potential to grow.As the number of tenants in the industrial park continues to grow so will electricity demand and the client will meet that demand with additional Turbophase modules. Until then, the additional 8.5 MW of electricity generated by the Turbophase system will provide the generator will additional profits now since they won’t have to purchase as much power from the grid.

Over the course of the summer, despite the 12-hour cooldown periods required by the improvised cooling system, the Turbophase modules were over 97 percent available and enhanced the GT output by 3.2 GWh. As anticipated, due to the adjustments to accommodate an accelerated deployment schedule, Turbophase module availability was impacted by diesel supply, water supply, and the necessary 12-hour cooldown time associated with an open cooling water cycle that reduced operations to a 12-hour shift. The Turbophase modules would otherwise be available and operating 24 hours a day. Still, 12-hour availability is more cost effective than current options to increase GT output. One option is to install a chiller to cool inlet air, but the chilled water is only available for six hours because a chiller takes 16 to 18 hours to chill water. The other available option is to build a peaking GT plant, but this is time and capital intensive and still subject to inefficient power output at high ambient air temperatures.

As measured during the two performance tests, the demonstration met the predicted system performance boost. Each Turbophase module added 4.25 MW at 8,650 BTU/kWh to the GT, for a total of 8.5 MW at 8,100 heat rate. By extrapolating the Turbophase output from the current firing temperature of 2,370F to the design point of 2,420F, the output increases to 4.5 MW at 7,600 BTU/kWh heat rate. An installation of 5 modules would result in an output increase of 22.5 MW. At 122°F (50°C) ambient air temperature, this results in a 19% output increase and 3.5% heat rate improvement. An installation of 7 modules would result in an output increase of 31.5 MW. At 122°F (50°C) ambient temperature, this results in a 26% output increase and a 5% heat rate improvement.

Market Background

Powerphase recently installed two Turbophase modules at a Malaysian high-tech park, one of several projects it has underway in Asia. Ensuring reliable and efficient natural gas capacity is a challenge in the fast-growing Southeast Asian grid. Southeast Asia’s hot climate is a challenge for efficient CCGT operation because hotter ambient temperatures reduce air density and GT combustion efficiency. Turbophase can boost performance in hot conditions, and has a small footprint that minimizes infrastructure needs where there is limited space. Developing island infrastructure can be challenging due to limited land availability. Turbophase technology is modular, compact, and can be integrated into an existing plant’s footprint so Southeast Asian plant operators don’t have to undertake new land, transmission, or fuel supply pipeline surveying, permitting, design, and construction.

Powerphase takes a consistent engineering approach for all its projects. The Turbophase system implementation plan began with a feasibility study, followed by a turnkey pilot project and full implementation designed to support future growth. Powerphase engineers estimate that the power plant could increase its generating output by 10 percent, with 8 Turbophase modules, while building out far less than tenth of the plant’s current footprint.

Powerphase permitted the project in May 2017, installed the Turbophase system within two months, and began pilot operation in late October. Powerphase will complete the pilot run in 60 days. Powerphase anticipates the project will be fully operational by Summer 2018 with the potential to grow.As the number of tenants in the industrial park continues to grow so will electricity demand and the client will meet that demand with additional Turbophase modules. Until then, the additional 8.5 MW of electricity generated by the Turbophase system will provide the generator will additional profits now since they won’t have to purchase as much power from the grid.

Over the course of the summer, despite the 12-hour cooldown periods required by the improvised cooling system, the Turbophase modules were over 97 percent available and enhanced the GT output by 3.2 GWh. As anticipated, due to the adjustments to accommodate an accelerated deployment schedule, Turbophase module availability was impacted by diesel supply, water supply, and the necessary 12-hour cooldown time associated with an open cooling water cycle that reduced operations to a 12-hour shift. The Turbophase modules would otherwise be available and operating 24 hours a day. Still, 12-hour availability is more cost effective than current options to increase GT output. One option is to install a chiller to cool inlet air, but the chilled water is only available for six hours because a chiller takes 16 to 18 hours to chill water. The other available option is to build a peaking GT plant, but this is time and capital intensive and still subject to inefficient power output at high ambient air temperatures.

As measured during the two performance tests, the demonstration met the predicted system performance boost. Each Turbophase module added 4.25 MW at 8,650 BTU/kWh to the GT, for a total of 8.5 MW at 8,100 heat rate. By extrapolating the Turbophase output from the current firing temperature of 2,370F to the design point of 2,420F, the output increases to 4.5 MW at 7,600 BTU/kWh heat rate. An installation of 5 modules would result in an output increase of 22.5 MW. At 122°F (50°C) ambient air temperature, this results in a 19% output increase and 3.5% heat rate improvement. An installation of 7 modules would result in an output increase of 31.5 MW. At 122°F (50°C) ambient temperature, this results in a 26% output increase and a 5% heat rate improvement.

By The Numbers

Project Details
Engine Type GE 6B
Configuration Combined Cycle
Megawatts as Installed 4.25 MW Per CT
Megawatts Potential 4.25 MW Per CT
Red. Use of Grid Power Yes
Efficiency Potential Yes

How It Works

Gas Turbines draw ambient air into their axial flow compressor, increasing the temperature and pressure of the air. The air then flows into the combustor where fuel is added proportionate to the amount of air mass flow and the mixture is ignited. This high-energy gas now expands through the turbine stages, creating mechanical torque to drive the gas turbine’s compressor and the net torque drives the generator producing electrical power.

The challenge faced by all gas turbines is that as ambient temperature or elevation rises, the density of the air naturally decreases, reducing the mass flow into the gas turbine. This reduced mass flow results in reducing the fuel flow proportionately to hold turbine inlet temperatures constant. This results in lower output.

Turbophase restores the mass flow that is naturally missing by injecting air into the compressor discharge. The gas turbine control system reacts naturally and adds a proportionate amount of fuel to account for the increase air mass flow, resulting in constant combustion and turbine inlet temperatures. The increased mass flow through the turbine section increases the mechanical torque to the compressor and generator.

Turbophase is a packaged system with a reciprocating engine driving a multi-stage, intercooled centrifugal air compressor. Air is drawn into system to ventilate the system and provide air to the compressor. The compressor air filtration system mirrors the air quality of the gas turbine and then is compressed by the first stage of the air compressor and then cooled. The inter-cooled process is repeated through four or five stages, depending on the desired pressure, resulting in less power required per pound of air compressed compared to the axial compressor in a gas turbine. After the final stage of compression, the compressed air flows directly into the recuperator, a heat exchanger which transfers the waste heat of the reciprocating engine exhaust into the compressed air. The Turbophase module can generate air at gas turbine compressor discharge pressure and temperature 30 to 40% more efficiently than the gas turbine itself.

A Turbophase system can have several modules and each module produces a certain mass flow of pressurized hot air. Each module is factory acceptance tested to ensure quality including correct air pressure and temperature prior to shipment to the power plant site. Depending on the size of the gas turbine, and the requirements of the power plant, a Turbophase system may have 1 module or more than 10 modules. Each module is approximately 32 feet long by 8 feet wide by 18 feet tall at its highest point. A typical Turbophase installation requires no unplanned outage at the plant.

powerphaase_turbophase-air-injection

Customer Challenges

While Asian countries are adding significant amounts of renewable power to replace coal, with a 2-3 percent annual increase in investment, a significant amount of gas-fired power is still needed. The International Energy Agency (IEA) has said gas will be increasingly adopted over coal by 2025, due largely to Asian countries’ air pollution concerns. With fast growing electricity demands, Asian nations need clean energy resources that can be

quickly deployed. One possible solution is to boost their existing natural gas generating capacity, which can help them get the most out of existing infrastructure while developing more renewable and gas-powered generation.

Ensuring reliable and efficient natural gas capacity is a challenge in the fast-growing Southeast Asian grid. All over the world, electricity market operators dispatch gas turbines in order of efficiency. The last turbine can be up to 30 percent less efficient than the first one that came online. Installing Turbophase on the grid allows the grid operator to shut off the least efficient turbines. Turbophase systems can be installed very quickly and deliver significant amounts of incremental power. They can be deployed around the entire power grid at existing plants, eliminating the challenges associated with new build such as land acquisition, transmission connections, and fuel sourcing.

Southeast Asia’s hot climate is a challenge for efficient CCGT operation because hotter ambient temperatures reduce air density and GT output. One option to increase GT output is a chiller.. However, chillers can only run 6 hours a day while parasitically reducing electricity output from the turbine because they draw power from the turbine to refrigerate the water for 16 to 18 hours a day. A Turbophase system is superior to a chiller, as it can be available 24 hours a day to boost air flow to the CCGT as long as it has a continuous air and power supply.

Besides boosting plant efficiency, Turbophase has a small footprint. Island nations throughout Southeast Asia have limited available land. With Turbophase, island plant operators don’t have to face new land, transmission, or fuel supply challenges because the technology is modular and can be integrated into an existing plant’s footprint. A Turbophase module is packaged as a short shipping container, which can be flexibly located around the plant or even up to 1 kilometer away from the GT.

powerphaase_turbophase-air-injection

Project Milestones

Powerphase has installed two air-cooled Turbophase modules on two CCGT plants, at a Malaysian high-tech park, to provide up to 50 MW of additional capacity. The project began at the beginning of 2017, with permits obtained in May, and construction completed over Summer 2017. In January 2017, Powerphase signed an agreement with the customer and then spent about 4 months preparing drawings and preparing project supplies.

After breaking ground in late May, Powerphase prepped the installation area by reinforcing wet ground in the area with 12- to 18-meter pilings to support concrete platforms for the Turbophase system. The Turbophase modules and roof skids for the auxiliary air cooling systems arrived the first week of July. The roof skids are modular and took only one shift to install on top of the Turbophase modules, which is a plug-and-play process of assembling the box support on the ground, lifting it with cables and aligning it with the Turbophase module, bolting it into place, and then lifting the skid and pinning that onto the box support. With all the modular pieces arranged and staged, the Powerphase team completed the Turbophase system assembly in four days and had it fully commissioned and running within two weeks.

In parallel with Turbophase module assembly, the Powerphase team was developing integration infrastructure between the Turbophase system and the plant. The team installed the head-end pipeline, a pipeline system to collect Turbophase module output and feed it to the gas turbines, and an electronics control center to control each Turbophase module and interface with the GT.

The Powerphase team designed a custom air pipe and fuel supply line. The plant needed the air pipe to traverse 220 meters to connect the Turbophase system to the gas turbines. The air pipe took 3 to 4 weeks to complete, and upon completion just needed to connect to the Turbophase module output nozzles. Powerphase designed the air piping system to support future growth, using a 12-inch diameter pipe that can support up to 8 Turbophase modules. The gas supply line follows a similar path to the air pipe, connecting the plant’s gas supply and Turbophase system. The gas line is a 4-inch diameter pipeline that fuels the Turbophase modules at a low pressure, 5 psi. The exhaust system was also custom designed to meet local environmental protection requirements of being at least 1 meter above structure with no bends. Typically, Powerphase would install an exhaust pipe with a 90-degree bend, but had to change alignment and add ports to top of stack to meet environmental requirements

The Turbophase electronics enclosure was connected to the customer’s electronic switchyard, via 180-meter heavy gauge 450V 3-phase cables and newly installed breakers. To ensure full Turbophase system availability, the Powerphase team installed three cables, one per each installed Turbophase module and a spare cable. As a result, if the plant operator took down the switchboard, it would not reduce Turbophase module availability.

powerphaase_turbophase-air-injection

Next Steps

The Malaysian natural gas power plant is fortunate to have a large footprint. It has room for growth, with enough space for 4 new GTs in future, and corresponding air-cooled condensers. Powerphase engineers estimate that the power plant could increase its generating output by 10 percent, with 8 Turbophase modules, while building out far less than tenth of the plant’s current footprint.

The high-tech park uses all of the plant’s power, and anticipates significant growth. Having a reliable source of electricity is important to the high-tech park’s tenants. Today, the high-tech park is the Malaysian outpost of several western high-tech companies that include Intel and First Solar. It contracted Powerphase with the plan to support an incoming tenant that would build a new manufacturing plant, that wouldn’t have to rely on the public power grid resulting in a lower cost of power to the high-tech park customers and more profits for the generator.

In Summer 2018, when two more tenants move into the high-tech park, the Turbophase system will be operating 24 hours, 7 days a week to boost power generation. The high-tech park anticipates that with the new tenants, it will be using all of the GT electricity output and need to expand again.

powerphase_emblem

Become Generation Smart

  • This field is for validation purposes and should be left unchanged.